Cafe and clinic fit-outs differ from office fit-outs. There are regulated components (hygiene for clinics, gas and ventilation for cafes) and experience-driven components (lighting, acoustics, customer flow). This 8-week execution sequence is arranged so each phase does not disrupt the next.
Week 1: Survey & Measure
- Physical site survey: detail measurement, existing condition photos, structural constraint identification
- MEP survey (Mechanical, Electrical, Plumbing): outlet locations, water pipes, exhaust
- Building documents: confirm building management regulations for renovation (work hours, material loading procedures)
- Brief alignment: visual direction (moodboard), target daily traffic, operational flow
Skip this week = hidden cost in week 4-5 when hitting columns not shown in the original architect drawing.
Week 2: Design Development
- Layout plan with customer flow (cafe: order - waiting - dine-in - exit; clinic: reception - waiting - consultation - treatment)
- Material palette (finishing, colors, main materials)
- 3D render 2-3 key angles
- Initial working drawing: kitchen/pantry for cafe, treatment room for clinic
Week 3: Engineering & Approval
- Detailed technical drawing: electrical layout, plumbing layout, HVAC
- BOM (bill of material) + spec list
- Client final approval, design freeze
- Order long-lead-time materials (kitchen equipment, HVAC unit, medical-grade material for clinic)
Week 4-5: Demolition & MEP
Heavy phase. Old partitions demolished, MEP lines torn out and reinstalled per new layout. This is the dustiest phase and must never run in parallel with finishing. Beginner brand mistake: starting finishing in week 4 to "save time". Result: dust ruins finishes, redo from scratch.
- Demolish existing partitions, ceiling, floor
- MEP rough-in: in-wall wiring, water pipes, AC ducting
- Testing: electrical load test, water pressure test, do not skip
- Plastering and floor screed
Week 6: Structural Finishing
- Install gypsum partitions + acoustics (clinics must be soundproof between rooms)
- Install ceiling + ceiling grid for lighting + AC
- Flooring: vinyl, tile, epoxy (clinics typically use epoxy or hygiene vinyl)
- Base coat painting
Week 7: Interior Fit-Out
This phase is where Magna custom furniture enters: cafe cashier counter, clinic reception, shelving, signage. All CNC-cut at Bekasi workshop, assembled onsite.
- Install counter, reception, display shelving (custom CNC)
- Install kitchen equipment (cafe) or medical equipment (clinic)
- Install decorative lighting + task lighting
- Install signage, wall graphics, menu board
- Soft furnishing: chairs, tables, booth seats
Week 8: Final Touch & Commissioning
- Paint touch-up, finishing details
- Deep cleaning throughout
- Commissioning: test all equipment, test lighting scenes, test AC
- Staff training (clinic: patient flow; cafe: kitchen and cashier workflow)
- Dress rehearsal: soft opening 1-2 days before grand opening
Variations by type
Cafe: kitchen is faster than a clinic treatment room, but ventilation (exhaust, grease trap) needs longer lead-time. Cafes in office buildings need stricter building management approval for kitchens.
Clinic: medical-grade material (epoxy floor, easy-clean wall panel, HEPA filter AC) has long material lead-time. Air circulation between rooms must be clear (positive pressure for treatment rooms). Regulations are stricter, operational permit documents can block grand opening if not yet issued.
Conclusion
Cafes and clinics can be ready in 8 weeks if the sequence is respected. Shorter timelines are possible but with compromises: weekend overtime, material substitutes, or reduced scope. Skipping any phase (especially MEP before finishing) almost always ends with expensive rework.